Rose Walk Close
Project type: Residential Eco-Retrofit
Project location: Newhaven, East Sussex
Above: A view of the completed project looking from the refurbished living room into the new studio space in the extension. Photo credit: Deeper Green
Above: The street elevation (north) of the finished project with the new extension visible on the left hand side of the house.
Photo credit: Deeper Green
Above: The first floor bedroom created in the new extension. Cork flooring was used throughout the upper floor.
Photo credit: Deeper Green
Above: The newly constructed porch with its delivery hatch and letter box.
Photo credit: Deeper Green
Above: The porch interior includes a post box beneath the delivery cupboard. The porch is partially insulated and includes a small frost protection heater. Photo credit: Deeper Green
Above: The original house included a double garage built up to the boundary. Photo credit: Deeper Green
Above: Thermal imaging revealed the extent of heat loss through the cavity walls. Note the dark purple colour of the blockwork mortar coursing and the window lintel which indicates these elements are cold and therefore convey more heat energy on cold days. Photo credit: Deeper Green
Above: The purple colour of the thermal image indicates colder surfaces and therefore greater heat loss. What you see here in purple are the wall studs, the flat roof joists and the triangular cheek of the dormer wall above the slope of the roof pitch. Photo credit: Deeper Green
Above: During the demolition work, the state of the injected wall insulation was revealed. Note how much the formaldehyde insulation has shrunk and the air gaps across and especially behind the insulation. These voids contribute to nullifying the insulative effect. The proposals included for removing and replacing with bonded cavity bead insulation.
Above: Careful attention was given to achieving an efficient thermal envelope around the existing building. Image credit: Deeper Green
Deeper Green were asked to extend and make more energy efficient a draughty late-1960s-built chalet bungalow on an exposed site high above the town of Newhaven. The project was complete in the autumn of 2026. The house now requires around 40% less energy to heat it, makes about 107% of its own annualised energy needs and has the ability to accommodate multi-generational family living.
Assessing the existing context
Due to its exposed and high location close to the English Channel, the house suffered from high levels of thermal discomfort in the winter particularly when windy. A previous owner had had the cavity walls filled with formaldehyde insulation which had cracked, shrunk and, in various places, dropped. This had led to the creation of significant pockets of cold air on the warm side of the injected material. U-PVC double-glazed windows had been fitted without due regard for airtightness and the suspended timber ground floor cumulatively added to the draughty nature of the interiors.
Deeper Green’s thermal camera survey underpinned the findings of the scoping study. The original timber frame dormers and the cavity blockwork of the ground floor were revealed to have high levels of heat loss on a cold day.
The proposals
Our clients were realistic about the budget and we set about scoping the most sensible eco-retrofit strategy of the existing building as well as doing a spatial study for a new extension and a complete rearrangement of the ground floor. Deeper Green’s Eco-Retrofit Scoping Study consolidated on a suit of upgrades that would result in a reduction of heating demand from around 6.1kW peak to around 3.5kW, even with the increased volume of the new extension. This was a 42% reduction. This paved the way for the replacement of the existing gas-fired boiler with an all-electric form of heating, chiefly supplied by an air source heat pump. The new extension was to take the place of an existing double-garage. This increased the habitable area of the building from 100m2 to 142m2 – a floor area increase of around 30%.
Additionally, the clients wanted a new entrance porch and a sauna and a shower room on the ground floor. Some of the 142m2 of habitable area of the building was in fact completed as a ‘Garden Room’. As the space was mainly intended for storage, it was not to be heated. However, the room is fully insulated and has dormant underfloor heating fitted into the screed. Thus, the space is future-proofed for an easy ‘regulations-compliant’ conversion to habitable space, if needed.
The final contract sum was around £343.5K + VAT with some elements delivered under the Government’s 0% VAT boiler replacement scheme.
Low environmental impact construction
Buildings with low or zero-carbon impacts in operational energy use, highlight the need to minimise global warming impacts of the actual construction – commonly known as ‘embodied carbon impacts’. Apart from the ground floor construction, which incorporates a 150mm thick concrete slab, concrete roofing tiles and an outer leaf of locally-manufactured brick on the new extension, the majority of the building materials used were of bio-based (grown) origins.
For instance the timber framed porch used locally grown and manufactured coppiced sweet chestnut external cladding. This is a durable and dimensionally stable material which provides economic support for the woodlands of the Sussex Weald. Best of all, the coppice growing technique is the fasted way of growing hardwoods and all the material is of course locked carbon removed from the atmosphere through photosynthesis.
Vast amount of UK-grown and manufactured hemp insulation was used in the project. Hemp is grown and harvested within a single season so it is a fabulous means of locking carbon dioxide out of the atmosphere and into buildings. Together with the timber frame and wood flooring and cladding, this insulation greatly offsets some of the embodied carbon of the concrete used in the project.
Above: Solar electric panels (PVs) mounted on the south-facing roof pitch of the house have a near perfect orientation. Photo credit: Deeper Green
Above: The Battery Energy Storage System (BESS) can hold up to 11kWh of energy. This allows the house to store energy created during the day, for use after dark. Photo credit: Deeper Green
Above: The Continuous Mechanical Extract Ventilation system (cMEV) extracts stale air from the ‘wet spaces’ of the house (bathrooms, kitchen, utility etc), which in turn encourages fresh incoming air to enter the house through trickle vents in the windows. Photo credit: Deeper Green
Above: The Air Source Heat Pump (ASHP) external unit provides a maximum heating capacity of 7kW, easily enough to cope with the minimal heat loss performance of the house. Photo credit: Deeper Green
Zero-carbon energy generation
The house now requires around 40% less energy to heat it and makes about 107% of its own annualised energy needs.
Heating
The energy efficiency upgrades made to the external fabric of the house (roof, walls and ground floor) made it possible to install an electric source of heat energy – an air to water heat pump (ASHP). One of the costliest elements of the project was to renew the ground floor construction. Part of this decision was predicated on it giving us the opportunity to introduce an underfloor heated screed. Heat pumps are most cost-effective to run with low flow temperatures on the space heating network. And, with such a large area of underfloor heating on the ground floor and enlarged radiators used on the first floor, the refurbished house can now bank on cost-efficient running of the ASHP.
Ventilation
Ventilation is an often overlooked ingredient in energy-efficient retrofits. As buildings become more airtight, the need for a more capable and dependable form of ventilating in the house becomes critically important. Otherwise, excessive moisture and airborne pollutants can build-up in the internal environment which in turn can harm occupant respiratory health.
At Rose Walk Close, a Continuous Mechanical Extract Ventilation system (cMEV) was selected. It works by extracting stale air from the ‘wet spaces’ of the house (bathrooms, kitchen, utility etc), which in turn encourages fresh incoming air to enter the house through trickle vents in the windows. In this way, air is constantly moving inside the house and the large single fan unit is super quiet and uses minimal electrical energy.
On-site energy generation
The new building has 14 solar electric panels, producing an impressive 6.3kW peak. Not only that, main south-facing pitch has near optimum orientation and very little over-shading. It is virtually a mini-power station.
The solar panels work in conjunction with a Battery Energy Storage System (BESS) which can hold up to 11kWh of energy. This allows the house to store energy created during the day, for use after dark. In winter, it can also charge-up on cheap electricity tarrifs at night to power the heating system during times of minimal solar collection. Estimates suggest that, because the house can make more energy than it is likely to use, the house can sell electricity to the grid when the purchase price per kWh is highest. In theory, this will make for a quick pay-back period and, from then on, produce a modest income for the homeowners.
Construction overview
Design strategies included:
Retrofitted loft floor with 2 x 100mm hemp quilt and loft boarding | U-value: 0.20W/m2K
Retrofitted dormer roof upgraded with 140mm PIR insulation | U-value: 0.15W/m2K
Retrofitted dormer walls (above roofline)upgraded with 100mm hemp quilt between studs and 80mm PIR insulation on cold side of studs | U-value: 0.16W/m2K
Retrofitted dormer walls (below roofline) upgraded with 100mm hemp quilt between existing studs and between new 100mm deep softwood rails with breather membrane over | U-value: 0.20W/m2K
Existing formaldehyde cavity insulation removed and new bonded cavity bead insulation injected | U-value: 0.50W/m2K
New extension walls with outer brick leaf, cavity and timber studs and service zone creating 225mm depth of hemp quilt | U-value: 0.17W/m2K
New ground bear slab (throughout) with 2 x 75mm PIR flooring insulation and gas membrane
U-value: 0.12W/m2K
Retrofitted eaves floor with 200mm existing mineral quilt and new 100mm hemp quilt over | U-value: 0.14W/m2K
Existing double-glazed uPVC windows overhauled | U-value: 1.8W/m2K (estimated) and new extension windows: triple-glazed | U-value: 0.8W/m2K
New porch enclosure cad in locally grown coppiced sweet chestnut
New air source heat pump external unit (7kW -rated)
New photovoltaic solar panels (6.4kW peak) fitted with 11kWh battery energy storage system
Replacement interlocking conrete roof tiles
EPDM single-ply membrane flat roof covering
Sliding wall panel and 'secret' library shelving
Stripping out
Out of the old rafter zone, the project team were able to salvage a substantial amount of mineral wool quilt which was subsequently reused for acoustic insulation in the floors and partitions.
Timber frame construction offers many benefits to the environment and helps create great levels of thermal comfort for the occupants.
Dormer walls of the extension above and below the roofline shown prior to the installation of the 75mm deep insulated service zone.
The foreground shows the existing dormer walls where the plasterboard was retained and all the insulation was applied between and the outside of the studs.
The original dormer walls had the lintels replaced over the windows.
The original dormer walls now with hemp insulation between the studs (prior to racking board, 80mm PIR, battens and hung concrete tiles being fitted)
The original deck of the dormer wall had to be removed prior to a new 'warm roof' construction being fitted to the top of the joists.
The existing and new dormer roofs were insulated with an impressive 140mm thick slab of PIR.
Vast amount of UK-grown and manufactured hemp insulation was used in the project. Hemp is grown and harvested within a single season so it is a fabulous means of locking carbon dioxide out of the atmosphere and into buildings. Together with the timber frame and wood flooring and cladding, this insulation greatly offset some of the embodied carbon of the concrete used in the project.
As the site was in an area of raised radon gas, a special membrane was used above the concrete slab.
Specialist heat resistant insulation was used in the sauna.
Above: The first floor extension walls showing the inner leaf of hemp quilt used to form a service zone (warm side of the stud zone). Photo credit: Deeper Green
Team credits:
Client: Private / domestic
Architects: Deeper Green
Main Contractor: Jove Group Limited